06.03.06
The Last Few Months
The last few months have been productive. We have completed all of the exterior walls and interior framing, in anticpation of the pre-roofing inspection. The inspector visited the building on Friday and said that the next inspection takes place after the work is complete on the sub-roof decking (2 x 6 tongue and groove) but before the roof itself goes on the building.
We have had the entire building pressure washed with bleach and it looks great. Click here for pictures of the building after its bath.
A group of teens and adults is arriving today from Johnson City, TN (this is their third annual trip) to work on the building and property next week. They will spend most of their efforts clearing thick brush and sealing the building’s exterior walls. We look forward to seeing old friends and new faces and worshipping with them tomorrow.